RPO & RECs

GERC has issued order for Renewable Power Obligations (RPO) which is to be compiled by distribution companies, captive power project and open access purchasers. Each of these shall purchase electricity (in kWh) from renewable energy sources, at a defined minimum percentage of total consumption in a year.

GERC has issued an order on RPO for the year 2012-13, wherein 7% is the minimum quantum of purchase (%) from renewable energy sources (in kWh), of which 5.5% is to be from wind energy, 1% from solar energy and 0.5% from Biomass, Bagasse and others.

RPO Order is provided here

Download Pdf

Procurement of Energy From Renewable Sources  April Р2010

Download Pdf

Procurement of Energy From Renewable Sources (Order No. 7 of 2010) July – 2010

Download Pdf

 Procurement of Energy From Renewable Sources (First Amendment) Regulations Р2014

Download Pdf